Create Routings
Manufacturing companies use routings to visualize and direct the manufacturing process.
The routing is the basis of process scheduling, capacity scheduling, scheduled assignment of material needs, and manufacturing documents.
As for production BOMs, the routings are assigned to the manufacturing end item. A routing holds master data that captures the process requirements of a given produced item. Once a production order is created for that item, its routing will govern the scheduling of operations as represented on the Prod. Order Routing page under the production order.
Before you can set up a routing, the following must be in place:
- Item cards are created for parent items that take part in manufacturing. For more information, see Register New Items.
- Production resources are set up. For more information, see Set Up Work Centers and Machine Centers.
To create a routing
Choose the icon, enter Routings, and then choose the related link.
Choose the New action.
Fill in the fields as necessary. Hover over a field to read a short description.
In the Type field, select Serial to calculate the production routing according to the value in the Operation No. field.
Select Parallel to calculate the operations according to the value in the Next Operation No. field.To edit the routing, set the Status field to New or Under Development. To activate it, set the Status field to Certified.
Proceed to fill in the routing lines.
In the Operation No. field, enter the number of the first operation, for example, 10.
In the Type field, specify which kind of resource is used, for example, Work Center.
In the No. field, select the resource to be used, or type it in the field.
In the Routing Link Code field, enter a code to connect the component to a specific operation. For more information, see To create routing links.
In the Run Time and Setup Time fields, enter the process times needed to perform the operation.
Note
Setup time is calculated per production order, whereas run time is calculated per produced item.
In the Concurrent Capacities field, specify how many units of the selected resource are used to perform the operation. For example, two people allocated to one packing operation will halve the run time.
Continue to fill in lines for all operations involved in producing the item in question.
To copy lines from an existing routing, choose the Copy Routing action to select existing lines.
Certify the routing.
You can now attach the new routing to the card of the production item in question, by filling in the Routing No. field. For more information, see Register New Items.
Note
Remember also to recalculate the item's standard cost from the Item card: Choose the Manufacturing action, select the Calc. Standard Cost action, and then select the All Levels action.
To create routing links
You can create routing links to connect components to specific operations in order to retain their relationship even though the production BOM or routing is modified. It also facilitates just-in-time flushing of components, namely when the specific linked operation starts, not when the complete production order is released. For more information see Flush Components According to Operation Output.
Another important benefit is that linked components and operations are displayed in a logical process structure when you use the Production Journal page for output and consumption posting.
Choose the icon, enter Routings, and then choose the related link.
Open the routing that contains the operations that you want to link.
Make sure the routing status is Under Development.
On the relevant routing line, in the Routing Link Code field, select a code.
Proceed to add different routing link codes to other operations in the routing, if relevant.
Note
You should not use the same routing link code in different operations on a routing because you may incorrectly link a component to two different operations, so that it is consumed two times.
It is a good idea to name the routing link code after the operation in order to ensure operation-specific routing links.
Set the routing status to Certified.
Routing link codes are now assigned to operations. Next, you must create the actual link by assigning the same codes to specific components in the relevant production BOM.
Open the Production BOM that contains the components that you want to link to the above operations. For more information, see Create Production BOMs.
Make sure the BOM status is Under Development.
On the relevant production BOM line, in the Routing Link Code field, select the code that you have just assigned to the relevant operation.
Proceed to add routing link codes to other components according to the unique operations where they are used.
Set the production BOM status to Certified.
Note
To enable the routing links on an existing production order, you must refresh the production order. For more information, see Create Production Orders.
The selected components will now be linked to the selected operations when you create or refresh a production order using the production BOM and routing in question. This is visible on the Prod. Order Components page under the production order, and here you can also remove and add the defined routing link codes at any time.
To assign personnel, tools, and quality measures to routing operations
If you require personnel with qualifications, special knowledge, or special authorization for an operation, you can assign these personnel to the operation. In addition, you can assign tools and quality requirements to the operation. This procedure describes how to assign personnel. The steps are similar for other types of operation information.
- Choose the icon, enter Routings, and then choose the related link.
- Open the relevant routing.
- On the Lines FastTab, select the line that you want to process, choose the Operations action, and then choose the Personnel action.
- Fill in the fields on the Routing Personnel page.
- Choose the OK button to exit the page. The entered values are copied and assigned to the operation.
To create a new versions of a routing
The version principle enables you to manage several versions of a routing. The structure of the routing version corresponds to the structure of the routing consisting of the routing version header and the routing version lines. The basic difference is defined by the starting date.
Choose the icon, enter Routings, and then choose the related link.
Select the routing to be copied, and then choose the Versions action.
On the Routing Versions page, choose the New action.
Fill in the fields as necessary.
In the Version Code field, enter the unique identification of the version. Any combination of numbers and letters is permitted.
The newly created version is automatically assigned the status New.
To create operation lines, select the first blank line, and then fill in the Operation No. field according to the sequence of operations.
The operation lines are sorted in ascending order by operation numbers. To be able to make changes later, we recommend you to select adequate step widths. The Next Operation No. field refers to the following operation. The number of the operation can be entered directly.
When the routing version is completed, setting the Status field to Certified.
The time validity of the version is specified by the Starting Date field.
See Also
Create Production BOMs
Setting Up Manufacturing
Manufacturing
Planning
Inventory
Purchasing
Working with Business Central
Note
Can you tell us about your documentation language preferences? Take a short survey.
The survey will take about seven minutes. No personal data is collected (privacy statement).