Flush Components According to Operation Output
You can define different flushing strategies, to automate registering of consumption of components.
For example, if a production order to produce 800 meters requires 8 kg of a component, then when you post 200 meters as output, 2 kg are automatically posted as consumption.
This functionality is useful for the following reasons:
Inventory Valuation
Value entries for output and consumption are created in parallel as the production order progresses. Without routing link codes, the inventory value will increase as output is posted and then decrease at a later point in time when the value of component consumption is posted together with the finished production order.
Inventory Availability
With gradual consumption posting, the availability of component items is more up-to-date, which is important to maintain the internal balance between demand and supply. Without routing link codes, other demands for the component may believe that it is available as long as it is pending a delayed consumption posting.
Just-in-Time
With the ability to customize products to customer requests, you can minimize waste by making sure that work and system changes only occur when it is necessary.
You can achieve that by combining backward flushing method and routing link codes so that the quantity that is flushed for each operation is proportional to the actual output of the finished operation. For items that are set up with backward flushing method, the default behavior is to calculate and post component consumption when you change the status of a released production order to Finished. If you also define routing link codes, then calculation and posting occurs when each operation is finished, and the quantity that was actually consumed in the operation is posted. For more information, see Create Routings.
To flush components according to operation output
Choose the icon, enter Items, and then choose the related link.
Choose the Edit action.
On the Replenishment FastTab, in the Flushing Method field, select Backward.
Note
Select Pick + Backward if the component is used in a location that is set up for directed put-away and pick.
Choose the icon, enter Routings, and then choose the related link.
Define routing link codes for every operation that consumes the component. For more information, see Create Routings .
Important
Do not use same routing routing link for different operations in the routing, as it will lead to registration of consumption of component for each linked operation.
Choose the icon, enter Production BOM, and then choose the related link.
Define routing link codes from each instance of the component to the operation where it is consumed.
The consumption will be posted automatically when you register output. For more information, see Batch Post Output and Run Times
Flushing methods
The following table describes the available flushing method options that you can specify on Item cards and Stockkeeping Unit cards.
Option | Description |
---|---|
Manual | Requires that you manually enter and post consumption in the consumption journal. |
Forward | Automatically posts consumption according to the production order component lines. By default, the posting of component consumption occurs when you change the status of a production order to Released. However, if you use the Routing Link Code field on production order component lines, then posting occurs per operation when the operation starts. For more information, see How to: Create Routing Links. Note For forward flushing, the operation-specific posting that you obtain with routing link codes is based on the expected quantity that is defined on the component line. For information about operation-specific flushing based on actual output, see the description of Backward in this topic. If the location or resources where this component is consumed are set up with a default bin structure, then the item is consumed from the Open Shop Floor Bin Code. For more information, see How to: Set Up Basic Warehouses with Operations Areas. Important Forward flushing also occurs when you choose Refresh on a released production order that was created from scratch. On these directly created released production orders, you cannot change bin information because the production order component lines are generated when you refresh the order, which at the same time forward flushes the components. Therefore, if you want to change bin information on production order component lines before forward flushing occurs, then that order must be created with the Planned or Firm Planned status. |
Backward | Automatically calculates and posts consumption according to the production order component lines. By default, the calculation and posting of component consumption occurs when you change the status of a released production order to Finished. However, if you use the Routing Link Code field on the production order component lines, then calculation and posting occurs when each operation is finished. Note Backward flushing and routing link codes can be combined so that the quantity that is flushed per operation is proportional to the actual output of that operation. For more information, see How to: Flush Components According to Operation Output. If the location or machine center where this component is consumed are set up with a default bin structure, then the item is consumed from the Open Shop Floor Bin Code. |
Pick + Forward | Same as for Forward flushing method, except it only works for locations that use directed put-away and pick. Consumption is calculated and posted from the bin that is defined in the To-Production Bin Code field on the location or machine center after the component has been picked from the warehouse. Note If a component is set up with the Pick + Forward flushing method, then it cannot have a routing link code to an operation that is set up with the forward flushing method. The component would then be automatically flushed when the operation starts, which makes it impossible to request the pick activity. |
Pick + Backward | Same as for Backward flushing method, except it only works for locations that use directed put-away and pick. Consumption is calculated and posted from the bin that is defined in the To-Production Bin Code field on the location or machine center after the component has been picked from the warehouse. |
See Also
Create Production BOMs
Setting Up Manufacturing
Manufacturing
Planning
Inventory
Purchasing
Working with Business Central
Note
Can you tell us about your documentation language preferences? Take a short survey.
The survey will take about seven minutes. No personal data is collected (privacy statement).